PASO ROBLES – The County of San Luis Obispo Public Works and Granite Construction, Inc. have started construction on a permanent two-lane bridge on Chimney Rock Road at Franklin Creek (near Fawn Lane) that will replace the existing one-lane steel bridge. A traffic detour will be in place with a strict 15-mph speed limit. Residents and motorists are advised to use caution and adhere to advisory signs. Temporary traffic signals will be installed on either side of the construction detour. Construction is expected to be completed in winter 2026. Please contact Aaron Hope at [email protected] or 805-781-5262 for any questions.
1/5/26 to 9/18/26 – LANE AND ROAD CLOSURES FOR DAY AND NIGHT WORK for the NCSD Trunk Sewer Project on S. Frontage Rd (Tefft to Division). Day work lane closures (one lane to remain open): 1/5/26 to 5/8/26 (85 days of day work). Night work full road closure with detours (both lanes): 5/8/26 to 8/21/26 (30 days of night work).